pp-planer/.sisyphus
Thorsten Bus 8c2f8a5d0a chore: mark cts-bugfix-features plan as complete in boulder state
All 20 tasks completed:
- 6 implementation tasks
- 4 verification tasks
- 10 success criteria items

Status: complete
Active plan: null (no active work)
2026-03-02 11:22:29 +01:00
..
evidence feat: add CTS API request logging with searchable frontend UI 2026-03-02 11:01:48 +01:00
notepads docs: mark all tasks complete in cts-bugfix-features plan 2026-03-02 11:19:22 +01:00
plans docs: mark all tasks complete in cts-bugfix-features plan 2026-03-02 11:19:22 +01:00
boulder.json chore: mark cts-bugfix-features plan as complete in boulder state 2026-03-02 11:22:29 +01:00
COMPLETION_REPORT.md docs: add completion report for cts-bugfix-features plan 2026-03-02 11:21:16 +01:00